# How to Do a Ductwork Takeoff: A Step-by-Step Guide for HVAC Estimators

Customiser team, 18 November 2026. 6 min read.

## Key takeaways

- A ductwork takeoff is the schedule of quantities for the air side of a job: duct by system, size and gauge, fittings, dampers, terminals, ancillaries and plant connections.
- Work system by system from the drawing's own colour key or legend, and measure runs along their centre lines at the sheet's scale.
- Rectangular duct surface area per metre is 2 x (width + height); circular duct is π x diameter. An 800 x 200 duct is 2.0 m² per metre.
- Gauge comes from size and pressure class (DW/144 in the UK, SMACNA in the US) unless the specification overrides it.
- Read the specification against the drawings before bid day: damper types, access doors, insulation and testing are where scope goes missing.

Every ductwork price starts with a takeoff. Get the quantities wrong and no rate in your estimating system will save the job; leave out the fire dampers or the access doors and you have bought that scope for free.

**To do a ductwork takeoff, read the legend and schedules first, then work system by system: measure each duct run along its centre line by size and gauge, count the fittings, count the dampers, terminals and ancillaries, note plant connections, then read the specification against what you counted and list what is unclear as RFIs.** The result is a schedule of quantities, sometimes called a bill of quantities or schedule of rates, that your estimating system prices.

## What is a ductwork takeoff?

A ductwork takeoff, or duct takeoff, is the measured list of everything on the air side of a mechanical job. It is part of the wider HVAC takeoff, which also covers equipment and, on many jobs, pipework. A full ductwork takeoff usually includes:

- **Straight duct** by system, shape (rectangular, circular, flat oval), size, gauge and pressure class, in metres or feet.
- **Fittings:** bends, branches and tees, reducers and transitions, offsets, end caps and open ends.
- **Dampers:** volume control, fire, fire and smoke, smoke, motorised and non-return.
- **Air terminals:** grilles, diffusers, linear slots, disc valves and louvres.
- **Ancillaries:** attenuators, flexible duct, access doors and flexible connections.
- **Plant connections:** air handling units, fan coil units, MVHR units, fans and VRF indoor units.
- **Insulation, fire-rated ductwork and testing,** usually driven by the specification rather than the drawing.

## How to do a ductwork takeoff, step by step

1. **Gather the whole tender.** Ventilation layouts, sections and details, the legend or colour key, duct and equipment schedules, the particular specification and any materials and workmanship specification. Note drawing numbers and revisions, and which drawings the specification refers to that were not issued.
2. **Read the legend before the plan.** The legend tells you which line style or colour is supply, extract, fresh air, exhaust, kitchen extract or smoke extract, and which symbols are fire dampers, VCDs and terminals. Counting before reading it is how dampers get counted as fittings.
3. **Check the scale on every sheet.** Confirm the drawn scale against a printed dimension. A sheet plotted at the wrong size will throw every measured length off by the same ratio.
4. **Measure duct by system, size and gauge.** Measure each run along its centre line and record system, shape, size and length. Use the size printed on the drawing; where a size is not printed, mark the measured size as provisional and raise it.
5. **Count fittings.** Count bends (90° and 45°), branches, reducers and transitions, offsets and end caps per size. UK practice often prices fittings as an equivalent length or area of straight duct; follow your own estimating system's rules.
6. **Count dampers, terminals and ancillaries.** Count each by type and size: fire dampers at every compartment wall and floor the duct crosses, VCDs on branches, grilles and diffusers from the layouts and the terminal schedule, attenuators, flexible duct and access doors.
7. **Note plant connections.** List each air handling unit, fan, fan coil or MVHR connection, with who supplies the unit. On many jobs the unit is by the mechanical contractor and only the connection is in ductwork scope.
8. **Read the specification against the drawings.** Check materials, gauges, damper types, access door rules, insulation, finishes, leakage testing and cleaning. Where the spec asks for something the drawing does not show, or the drawing shows something the spec does not settle, write it down.
9. **Raise the RFIs and write the scope letter.** Turn every open question into an RFI before the tender closes, and list scope marked by others or by specialist so your quote says what is excluded.

## How do you calculate ductwork surface area and weight?

Ductwork is often priced on the area of sheet metal it uses (common in the UK) or on its weight (common in the US). Both start from the surface area per unit length.

```
Rectangular duct area per metre = 2 x (W + H)      (W, H in metres)
Circular duct area per metre = π x D               (D in metres)
Duct weight = area x sheet weight per unit area for the gauge
```

Galvanised steel sheet weighs about 0.906 lb/ft² at 26 gauge, 1.156 lb/ft² at 24 gauge, 1.406 lb/ft² at 22 gauge and 1.656 lb/ft² at 20 gauge. Use your supplier's figures.

*Worked example: two runs from one sheet*

| System | Size (mm) | Length (m) | Area per metre (m²) | Area (m²) |
| --- | --- | --- | --- | --- |
| Supply | 800 x 200 | 42.6 | 2 x (0.8 + 0.2) = 2.00 | 85.2 |
| Extract | Ø250 | 18.2 | π x 0.25 = 0.785 | 14.3 |
|  | **Total** |  |  | **99.5** |

> **Gauge follows size and pressure class.** The sheet thickness for a duct comes from its size and pressure class in the standard the job uses: DW/144 in the UK, SMACNA's HVAC Duct Construction Standards in the US. The particular specification can override it, so check before you apply a default table.

## What are the most common ductwork takeoff mistakes?

- **Missing fire dampers** where ducts cross compartment walls and floors that are only marked on the architect's fire strategy drawings. See [fire dampers and access doors in a ductwork takeoff](https://customiser.ai/blog/fire-dampers-access-doors-ductwork).
- **Access doors left out:** one is usually needed at every fire damper and at other in-duct items, and the specification may add more for cleaning.
- **Sizes assumed, not read:** a measured size is a guess until the drawing or schedule confirms it.
- **Spec scope not priced:** insulation, fire-rated ductwork, leakage testing and cleaning often live only in the specification.
- **Revisions:** a takeoff from P01 drawings priced against a P03 issue.
- **Scope by others not excluded:** if the drawing says a kitchen extract canopy is by specialist, say so in the quote.

## Should you do a ductwork takeoff by hand or with software?

By hand, with a scale rule and highlighters, works for a small job and is slow on a large one. On-screen takeoff tools let an estimator click along runs on a PDF, which is faster but still needs every run and symbol picked by a person. Automated HVAC takeoff software reads the drawings itself and returns the quantities for your team to check. We compare the three in [automated HVAC takeoff software: what to expect](https://customiser.ai/blog/automated-hvac-takeoff-software).

Whichever you use, the takeoff should keep a link from each quantity back to the place on the drawing it came from, so a checker can confirm it in seconds rather than measure it again.

## Frequently asked questions

### What is included in a ductwork takeoff?

Straight duct by system, size, gauge and length; fittings; dampers; grilles, diffusers and other air terminals; attenuators, flexible duct and access doors; plant connections; and the insulation, fire rating and testing the specification asks for.

### How do you calculate the surface area of rectangular duct?

Multiply the perimeter by the length: 2 x (width + height) x length. An 800 x 200 mm duct has 2 x (0.8 + 0.2) = 2.0 m² of surface per metre, so a 42.6 m run is 85.2 m².

### How long does a ductwork takeoff take?

It depends on the size of the job and the method. A small job by hand can take a few hours; a large commercial tender with many sheets can take an estimator several days, which is why many contractors use on-screen or automated takeoff software.

### Which standards set duct gauge?

In the UK, DW/144 sets sheet thickness by duct size and pressure class; in the US, SMACNA's HVAC Duct Construction Standards do. The project specification can override either.

## Related

- [Automated HVAC take-off](https://customiser.ai/hvac): How Customiser reads your ventilation layouts and specs and returns the schedule of quantities with its evidence.
- [Fire dampers and access doors in a ductwork takeoff](https://customiser.ai/blog/fire-dampers-access-doors-ductwork): Where they go, which standards apply and how to count them.
- [Automated HVAC takeoff software](https://customiser.ai/blog/automated-hvac-takeoff-software): Manual, on-screen and automated takeoff compared, and what to ask a vendor.